Factory License Approvals_Timelines
Factory Planning Gantt Chart
| Task No. |
Task | Start Date |
End Date |
Dur. (days) |
Depen dency |
Status | Action |
|---|---|---|---|---|---|---|---|
| 1 | Factory Plan Drawing | 20 | |||||
| 2 | Factory Plan Drawing Approval | 7 | |||||
| 3 | Factory Licence | 45 | |||||
| 4 | Form III - Holiday Approval | 20 | |||||
| 5 | Pressure Vessel Testing | 10 | |||||
| 6 | Stability Certificate | 30 | |||||
| 7 | Sanitary Certificate | 30 | |||||
| 8 | Fire Licence | 45 | |||||
| 9 | Professional Tax Reg. | 60 | |||||
| 10 | PCB (Air & Water Consent) - CTO | 30 | |||||
| 11 | PCB (Air & Water Consent) - CTE | 45 | |||||
| 12 | Notice of Opening - Form A | 0 | |||||
| Summary | |||||||